概要: 2.1.Installation work items主要工程量一览表Item Area Description Unit Qty序号 区域 项目名称 单位 工程数量 1 Supply and install cleanroom above ceiling and FAB L40 air plenum air dividers and associated doors洁净室供装,吊顶上方,FAB L40 压力通气口,空气分配器和相关门 Partition installation above ceiling吊顶上方隔板安装 ㎡ 7337 Single door installation单开门安装 Nos樘 2 Double door installation双开门安装 Nos樘 3 Access door installation通道门安装700www.67jzw.com*800 Nos樘 27 Access door installation通道门安装700*1600 Nos樘 3 2 Supply and instal
Intel(Dalian)FAB68 Project(F01P Package)英特尔(大连)F68生产厂房项目,标签:市政工程技术,市政工程施工方案,http://www.67jzw.com2.1.Installation work items
主要工程量一览表
Item Area Description Unit Qty
序号 区域 项目名称 单位 工程数量
1 Supply and install cleanroom above ceiling and FAB L40 air plenum air dividers and associated doors
洁净室供装,吊顶上方,FAB L40 压力通气口,空气分配器和相关门
Partition installation above ceiling
吊顶上方隔板安装 ㎡ 7337
Single door installation
单开门安装 Nos
樘 2
Double door installation
双开门安装 Nos
樘 3
Access door installation
通道门安装700www.67jzw.com*800 Nos
樘 27
Access door installation
通道门安装700*1600 Nos
樘 3
2 Supply and install temporary partition, pass thru, gowning room during construction as per MWZ protocol management’s requirements.
临时隔墙供装,通道,更衣室,按MWZ协议管理要求
Color steel sheet partition wall(partition)
彩钢板隔墙安装(隔间部分) ㎡ 5227
Single door installation
单开门安装 Nos
樘 8
Double door installation
双开门安装 Nos
樘 31
3 Install cleanroom ceiling system, include supply of all necessary associated hardware & non-outgassing type gasket / sealant (base offer, detail refer to "PDD's Appendix&nwww.67jzw.combsp; 2 : General notes to vendors)
安装洁净室吊顶系统,包括所有相关五金和非除气衬垫/密封剂(基价,详情见PDD附件2:供应商说明)
Square adjustor of hanger and fittings, excl. L<6000
吊点点位/配件(M10/L=6000)方形调节器及其以下不含 Set
套 30216
Square adjustor of hanger and fittings, excl. L<3000
吊点点位/配件(M10/L=3000)方形调节器及其以下不含 Set
套 10080
Square adjustor of hanger and fittings, excl. L<2000
吊点点位/配件(M10/L=2000)方形调节器及其以下不含 Set
套 2200
4 Install cleanroom “C” channel system, include supply of all necessary associated hardware
安装洁净室“C”槽钢系统,包括供应所有必需五金
Installation of ceiling support
吊顶支架安装 ㎡ 28885
5 Iwww.67jzw.comnstall cleanroom FFU system
安装洁净室FFU系统
Keel installation
FFU龙骨安装 ㎡ 30185
FFU installation
FFU安装 Ea
台 4713
Installation of blind plate
盲板安装 pcs 16415
6 Install cleanroom furniture
安装洁净室家具
7 Install cleanroom metal works, include supply of all necessary associated hardware
洁净室金属安装,包括供应五金
cat ladders (refer to drawing F68F300AK501)
爬梯 no 2
cat ladders (refer to drawing F68F300AK502)
爬梯 no 4
stairs (refer to drawing F68F300AK503)
楼梯 set&www.67jzw.comnbsp;4
protective handrails along F30 3657mm catwalk, (3.6m long per unit) with 100mm high epoxy powder coated toeboard (refer to drawing F68F300AK111, F68G000AK511, F68F000AK301, F68F000AK304, F68F000AK305,
扶手,沿F30 3657mm通道, (3.6m长/个),100高挡板,有环氧粉末涂层
Protective handrails (min. 1050mm high,L=7.2m long) with 100mm high epoxy powder coated toeboard along FAB L40 return air shafts with necessary accessories (refer to drawing F68F400AK163)
扶手(至少1050mm高,L=7.2m长),100高有环氧粉末涂层的挡板,沿FAB L40回风井,有配件 set 20
8 Install plywood coverage on FAB L30 waffle tables and FAB L40 structural purlin, include supply of adhesive tape around four sides of plywood, PVC sheet below plywood in FAB L30 www.67jzw.comwaffle tables
安装胶合板,FAB L30办公桌和FAB L40结构围檩,包括供应胶合板四边的胶带和FAB L30桌胶合板下的PVC板
PVC sheet protection, incl. single-side black/yellow adhesive tape
2mmPVC板保护/含单面黑黄胶带 ㎡ 10000
9 Supply and Install all necessary temporary structure during construction if required
施工期间供装临时结构