FIDIC设计采购施工(EPC)合同条件(银皮书英文版)

[08-22 14:23:58]   来源:http://www.67jzw.com  造价预算   阅读:8411

概要:They shall not, without the Employer’s consent, be copied, used or communicated to a third party by the Contractor, except as necessary for the purposes of the Contract.1.12 Confidential DetailsThe Contractor shall not be required to disclose, to the Employer, any information which the Contractor described in the Tender as being confidential. The Contractor shall disclose any other information which the Employer may reasonably require in order to verify the Contractor’s compliance with

FIDIC设计采购施工(EPC)合同条件(银皮书英文版),标签:工程预算学习,建筑工程概预算,http://www.67jzw.com
They shall not, without the Employer’s consent, be copied, used or communicated to a third party by the Contractor, except as necessary for the purposes of the Contract.
1.12 Confidential Details
The Contractor shall not be required to disclose, to the Employer, any information which the Contractor described in the Tender as being confidential. The Contractor shall disclose any other information which the Employer may reasonably require in order to verify the Contractor’s compliance with the Contract.
1.13 Compliance with Laws
The Contractor shall, in performing the Contract, comply with applicable Laws. Unless otherwise stated in the Particular Conditions:
(a) the Employer shall have obtained (or shall obtain) the planning, zoning or similar permission for the Permanent Works, and any other permissions described in the Employer’s Requirements as having been (or being) obtained by the Employer; and the Employer shall indemnify and hold the Contractor harmless against and from the consequences of any failure to do so; and
(b) the Contractor shall give all notices, pay all taxes, duties and fees, and obtain all permits, licences and approvals, as required by the Laws in relation to the design, execution and completion of the Works and remedying of any defects; and the Contractor shall indemnify and hold the Employer harmless against and from the consequences of any failure to do so.
1.14 Joint and Several Liability
If the Contractor constitutes (under applicable Laws) a joint venture, consortium or other unincorporated grouping of two or more persons:
(a) these persons shall be deemed to be jointly and severally liable to the Employer for the performance of the Contract;
(b) these persons shall notify the Employer of their leader who shall have authority to bind the Contractor and each of these persons; and
(c) the Contractor shall not alter it’s composition or legal status without the prior consent of the Employer.
2 The Employer
2.1 Right of Access to the Site
The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time (or times) stated in the Particular Conditions. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Employer’s Requirements. However, the Employer may withhold any such right or possession until the Performance Security has been received.
If no such time is stated in the Particular Conditions, the Employer shall give the Contractor right of access to, and possession of, the Site with effect from the Commencement Date.
If the Contractor suffers delay and/or incurs Cost as

www.67jzw.coma result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.
After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
However, if and to the extent that the Employer’s failure was caused by any error or delay by the Contractor, including an error in, or delay in  the submission of, any of the Contractor’s Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.
2.2 Permits, Licences or Approves
The Employer shall (where he is in a position to do so) provide reasonable assistance to the Contractor at the request of the Contractor:
(a) by obtaining copies of the Laws of the Country which are relevant to the Contract but are not readily available, and
(b) for the Contractor’s applications for any permits, licences or approvals required by the Laws of the Country:
(i) which the Contractor is required to obtain under Sub-Clause 1.13 [Compliance with Laws],
(ii) for the delivery of Goods, including clearance through customs, and
(iii) for the export of Contractor’s Equipment when it is removed from the Site.
2.3 Employer’s personnel
The Employer shall be responsible for ensuring that the Employer’s Personnel and the Employer’s other contractors on the Site:
(a) co-operate with the Contractor’s efforts under Sub-Clause 4.6     [Co-operation],and
(b) take actions similar to those which the Contractor is required to take under sub-paragraphs (a), (b) and (c) of Sub-Clause 4.8 [Safety Procedures] and under Sub-Clause 4.18 [protection of the Environment].

上一页  [1] [2] [3] [4] [5] [6] [7]  下一页


Tag:造价预算工程预算学习,建筑工程概预算工程资料 - 造价预算

上一篇:创建工程造价管理信息平台 实现全过程造价管理

《FIDIC设计采购施工(EPC)合同条件(银皮书英文版)》相关文章

会员评论


联系本站 | 免责声明 | 下载帮助 | 建筑资料下载 | 房地产资料 | 建筑资料库二 | 建筑课堂 | 建筑考试 | 装修设计 | 网站地图 | 收藏本站

Copyright 牛气建筑网 版权所有 All Right Reserved.

1 2 3 4 5 6 7 8 9 10